How Long Does General Contractor Take? Timelines and What to Expect
In Garland, a kitchen remodel permit can take two to four weeks for plan review alone. That delay never shows up in the contractor’s quoted “three-week project” timeline, but it eats calendar days just the same. Most homeowners plan around labor and materials and forget the third ingredient: the city’s review desk, the cabinet factory’s lead time, and the electrician’s already-booked schedule. This guide is about what actually stretches a remodel, phase by phase, and how to read a timeline honestly. We work in Garland every week, and we’ve watched more projects slip on paperwork and order timing than on tile work.
Quick Answer
A general contractor timeline for a typical home remodel runs four to six weeks for a bathroom, eight to twelve weeks for a kitchen, and four to eight months for an addition or whole-home remodel. The work itself is often the smallest part. Permit review, material lead times, and trade scheduling usually account for half the calendar.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
Table of Contents
- Phase-by-Phase: What a Real Timeline Looks Like
- Permits and Plan Review in Garland: The Hidden Weeks
- Material Lead Times You Should Know Before You Demo
- Timelines by Project Type: Kitchen, Bath, Addition, Whole Home
- Legitimate Delays vs. Contractor Mismanagement
- Why a Written Arrival Window Beats “We’ll Be There Monday”
- How to Read a Contractor’s Timeline Before You Sign
- Common Mistakes to Avoid
Phase-by-Phase: What a Real Timeline Looks Like
A remodel has five phases, and only one of them looks like actual construction. The others are waiting, ordering, and inspections. Here’s the sequence we use when we’re laying out a written schedule for a Garland homeowner.
- Design and material selection (one to three weeks). This is where you pick cabinetry, tile, fixtures and finish. If you choose KraftMaid or Wellborn cabinets, the ordering step happens here. If you choose Cambria or Silestone countertops, the slab selection happens here too. Skipping this step to “save time” always costs time later.
- Permit application and plan review (two to four weeks in Garland). The city reviews plans, checks trade licensing, and issues the permit. On a bathroom, this can be faster. On structural changes, expect the longer end.
- Material delivery and staging (one to four weeks). Cabinets are the big one. Tile, windows and specialty fixtures also drive this window.
- Demo and rough-in (one to two weeks). Tear-out, framing changes, electrical rough-in, plumbing rough-in. Rough-in means the pipes and wires that go behind the walls before anything is closed up.
- Finish and punch list (two to four weeks). Drywall, paint, tile, cabinets, countertops, trim, final inspection, and the walkthrough.
Added up honestly, a kitchen is eight to twelve weeks end-to-end. A contractor who tells you “three weeks” is either skipping the permit, ignoring lead times, or planning to move crews through your kitchen in a way that always produces callbacks. None of those are in your interest.
Permits and Plan Review in Garland: The Hidden Weeks
Permit review is the single most under-quoted phase of any Garland remodel. The City of Garland’s development services department reviews plans for structural changes, electrical updates, plumbing relocations, and anything that touches the building envelope. Standard residential review often runs two to four weeks. Complex structural work can push longer. And plan review is not the same as inspection time – after the work is done, a rough-in inspection and a final inspection each take days to schedule.
We’ve seen homeowners stuck in month three on a project they were told would be done by week six, all because the permit was started late. This isn’t Garland being slow. Every city in North Texas runs some version of this schedule. The problem is contractors who treat the permit as an afterthought and pad the timeline with a vague “we’ll need some time up front.”
Two things you should confirm in writing before signing anything:
- Permit pull date. When does the contractor expect to submit the application, and who is paying the permit fees? The answer should be a specific week in the schedule.
- Who is pulling the permit. A licensed general contractor pulls the permit under their license. If a contractor asks you to pull it as the homeowner, walk away. That’s a way to transfer liability to you.
We write permit review into every timeline we hand a homeowner. If you’re weighing contractors on a general contractor in Garland project, ask each one what their plan review lead time assumption is. The ones who have an answer are the ones who’ve actually pulled a permit in this city recently.
Material Lead Times You Should Know Before You Demo
2024 and 2025 have taught every contractor the same lesson: order before demo, not after. Once the kitchen is torn out, every extra week of waiting is a week of eating out and a week of port-a-potty rental. Here’s what we’re seeing on real Garland jobs right now.
- KraftMaid and Wellborn cabinetry: six to ten weeks from order to delivery on standard lines. Semi-custom options push toward ten to twelve. This alone can be the entire bottleneck on a kitchen.
- Windows (Therma-Tru doors and quality vinyl or fiberglass window lines): five to ten weeks depending on size and finish. Custom sizes run longer.
- Tile and stone (Cambria, Silestone, Caesarstone, James Hardie siding): in-stock items ship in one to two weeks. Slab selections with specialty finishes run three to five weeks.
- Fixtures (Kohler, Moen, Blanco, Delta, Toto, Grohe): most in-stock fixtures are two to three weeks. Specialty finishes and freestanding tubs run four to six.
- Roofing materials (Atlas shingles, Tamko underlayments): usually one to two weeks in this market, so the roof on your addition won’t hold up the schedule.
The takeaway: cabinets are the pacing item. A contractor who orders cabinets after demo day has already cost you four to six weeks. A contractor who orders the moment plans are approved has built a realistic timeline. This is exactly the kind of thing we itemize before demo starts.
Timelines by Project Type: Kitchen, Bath, Addition, Whole Home
Here’s what we quote when we’re honest, which is always. These are typical end-to-end numbers with permits and lead times included.
Bathroom remodel: four to six weeks
A standard bathroom remodeling in Garland – new tile, vanity, toilet, and shower – runs four to six weeks. A tub-to-shower conversion with a relocated drain is on the longer end. If you’re only replacing a vanity or re-grouting, you might be looking at one to two weeks and no permit.
Kitchen remodel: eight to twelve weeks
A kitchen remodeling in Garland sits at eight to twelve weeks end-to-end. The main variance is cabinet lead time and whether you’re changing the layout (which triggers plumbing and electrical work and longer permit review). Cosmetic-only kitchens – refacing, new countertops, no layout change – can run five to seven weeks.
Addition (room, garage conversion, primary suite): four to six months
Additions carry longer permit review and inspection cycles because they involve framing, foundation, and envelope work. Plan review alone can run four to eight weeks. Foundation and framing take two to four weeks. Finishes take another four to six. If plumbing or HVAC is being extended, add two weeks.
Whole-home remodel: five to eight months
A full interior remodel (all rooms at once, but living in the house) runs five to eight months. A whole-home remodel that requires the house to be vacant – often the better call when you’re moving walls and re-piping – can run four to six months. Both include permit review, material lead times, and trade sequencing across multiple crews.
Every project on this list includes a written price before we start, and the price on day one is the price on the invoice. If you’re trying to plan around work and school schedules, we’re happy to walk you through the timing on a specific job – see the Penhallow Remodeling Garland home page for the services we cover.
Legitimate Delays vs. Contractor Mismanagement
Some delays are real. Others are a contractor who didn’t schedule the electrician. You can tell the difference if you know what to look for.
Legitimate delays:
- City plan review came back with a comment and the plans need revision. This is common and it’s the city’s timeline, not the contractor’s.
- A cabinet factory pushed delivery six weeks. You should see the order confirmation date and the revised ship date in writing.
- Hidden conditions found during demo – rotted framing behind old tile, galvanized plumbing that failed pressure testing, or a structural beam that wasn’t on the plans. A written change order with a written price should appear before work continues on the hidden item.
- Weather delays on exterior work. In Garland, spring storms and summer heat both slow siding and roof installations.
Mismanagement:
- The permit was submitted late, or not at all. Ask for the permit number.
- The contractor forgot to order cabinets or windows until demo was underway.
- The same crew is on three jobs simultaneously and yours is the third.
- You can’t get a straight answer about which phase is active this week.
We’ve been called to rescue projects caught in the second list, and the difference usually comes down to one thing: the original contractor never wrote anything down. A written schedule with date ranges per phase is the single best defense you have.
Why a Written Arrival Window Beats “We’ll Be There Monday”
“We’ll be there Monday” is not a schedule. Monday is seven possible arrival times, and none of them are commitments you can plan your workday around. A written arrival window says something like “arrival between 8:00 and 9:00 a.m. Tuesday, and if we’re late, you’ll get a call before 8:15.” That’s a real commitment, and it’s what we do on every job.
Why does this matter so much on a long remodel? Because most of the time you’re not waiting for construction. You’re waiting for somebody to show up so your life can move forward. A homeowner in Garland who has to take a morning off work to let a plumber in has lost half a vacation day. Multiply that by ten or twelve visits over a two-month kitchen remodel, and a vague arrival window has cost you a week of paid time off without a single thing going wrong on the job itself.
The written arrival window is one of four commitments inside The Kingswell Way: say the price before the work, show up in the window we gave, leave the place cleaner than we found it, and stand behind the work in writing. That last part is our 365-Day Done Right Promise. If something we installed fails inside the guarantee period, we come back and fix it at no charge. The free return visit covers any repair that doesn’t hold. You get the arrival window on the front end and the guarantee on the back end, both in writing.
How to Read a Contractor’s Timeline Before You Sign
When a contractor hands you a timeline, read it like a contract, not a brochure. The best timelines break down by phase with date ranges and named dependencies.
- Every phase has a start week and an end week. Not “week 2-4” but specific calendar weeks that line up with your permit and your material order.
- Permit review is a line item. If it isn’t in the schedule, the contractor hasn’t accounted for it.
- Material order dates are visible. You should see “cabinets ordered week 1, delivery expected weeks 6-8” – not just “cabinets installed week 6.”
- Arrival windows are specific. Two-hour windows with a call if we’re late. Not “Tuesday, some time.”
- Hidden-condition language is honest. A good timeline tells you what happens if demo finds rotted framing – change order, written price, your approval, then work.
- The guarantee is on the same piece of paper. If the guarantee is on a separate flyer, it’s marketing, not a commitment.
We’ve been asked to review dozens of other contractors’ timelines, and the ones that fail this checklist always fail on the same two points: no permit phase and no material order dates. Fix those two and a schedule is honest. Ignore them and it’s fiction with good typography.
Common Mistakes to Avoid
- Signing a contract with no permit phase in the schedule. A Garland kitchen that doesn’t budget two to four weeks for plan review is already behind before the first truck rolls.
- Ordering cabinets after demo. Once the kitchen is torn out, you’re paying for hotel food and lost time while cabinets are in a factory somewhere in Indiana. Order before demo or push the demo date.
- Accepting “we’ll be there Monday” as a schedule. Monday is not an arrival window. Ask for a two-hour window in writing.
- Comparing contractors on total price alone. A $500-cheaper bid that skips the permit and the arrival window costs you thousands in delays and rework.
- Believing the “three-week kitchen” quote. It exists only if the homeowner is not living in the house, the layout doesn’t change, the cabinets are already on site, and the city does same-week review. None of those things are true on a typical Garland job.
- Not asking who pulls the permit. If the answer is “you do,” the contractor is transferring the inspection risk onto your house.
- Skipping the walkthrough before final payment. The punch list belongs before the last check clears. Never after.
See the difference
Before
After
Before
After
Before
AfterWhen to Call a Professional
Some things are worth a phone call rather than a DIY weekend. If your project involves moving walls, relocating plumbing or gas, updating electrical, or any structural work, call a licensed professional. If your “small” bathroom refresh has revealed rotted subfloor or failed tile substrate, stop and call – the repair is bigger than it looks. If you’re planning a remodel that needs a permit and a realistic schedule, this is where we help. Penhallow Remodeling Garland offers free estimates in Garland – call (844) 560-4146 to schedule yours. You’ll get a written price before any work starts, and a written guarantee on the finished project.
Frequently Asked Questions

A home remodel in Texas typically runs four to six weeks for a bathroom, eight to twelve weeks for a kitchen, and four to eight months for an addition or whole-home remodel. The variance comes from permit review time, material lead times, and trade scheduling, not from how long the hammering takes.
Plan review for a residential remodel permit in Garland usually takes two to four weeks, with structural changes often on the longer end. After work is done, rough-in and final inspections each take days to schedule. A contractor who leaves the permit out of the schedule is quoting you an impossible timeline. Call (844) 560-4146 for a free estimate that includes permit timing.
Most under-quoted timelines leave out permit review, cabinet lead time, or trade scheduling – often all three. Some contractors quote short to win the job and then blame the city or a supplier when things slip. Ask for a written phase-by-phase schedule before signing.
Standard cabinets from lines like KraftMaid or Wellborn are running six to ten weeks from order to delivery, and semi-custom options run longer. Order the cabinets before demo starts or your schedule will slide by a month or more.
Often yes, but it depends on the scope. A cosmetic kitchen can usually be lived in; a full gut with layout changes is harder on a family. We’ll tell you honestly at the estimate stage which category your project falls into. Call (844) 560-4146 to schedule a free estimate.
No – the price on day one is the price on the invoice. The only legitimate change is a hidden condition found during demo, and that always comes to you as a written change order with a written price. You approve before work continues.
The Bottom Line
The honest answer to “how long does a general contractor take” is: the work is fast, the calendar is long. A kitchen in Garland runs eight to twelve weeks because of the permit, the cabinets, and the trades – not the drywall. A bathroom runs four to six weeks for the same reasons. Ask any contractor for a phase-by-phase schedule with permit dates, material order dates, and two-hour arrival windows. If they can’t produce one in writing, the timeline is fiction.
Ready to get a real schedule and a written price? Call Penhallow Remodeling Garland at (844) 560-4146 for a free estimate. We’ll walk your project, give you a written phase-by-phase timeline, and back the work with our 365-Day Done Right Promise. Our technicians have up to 22 years of experience, and every job gets a written guarantee before the first cabinet is ordered.