A Penhallow company - serving Garland, TX
A remodeled kitchen with a wood island, painted cabinets and a plaster range hood

How Long Does a Kitchen Remodel Take? (Garland, TX)

Free Estimate on SiteCalls Answered by a Live Person, 24/7Background-Checked TechniciansA Local Team in Garland
A small remodeled galley kitchen with cabinets to the ceiling
A walk-in pantry with wood shelving
A remodeled kitchen with a waterfall island and wood cabinets
An open kitchen and dining area after a remodel
A galley kitchen opened up to the dining room with a new peninsula
A whole-home remodel with the living, dining and kitchen areas opened up
A second-story addition that matches the existing roofline
A walk-in shower with large-format tile and a built-in niche
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate
Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence
Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

How Long Does a Kitchen Remodel Take in Garland, TX? Plan on 3-6 Weeks, Plus a Week for What’s Behind the Walls

A typical Garland kitchen remodel takes 3-6 weeks of construction time on paper. But in a home built before 1975, budget an extra week for what comes out of the walls, because Garland’s aging housing stock has a near-perfect record of surprising contractors once demo starts. If you want to talk through your specific kitchen, call Penhallow Remodeling Garland at (844) 560-4146. A real person answers, day or night, and we’ll give you a written timeline before anything gets touched.

Garland sits in the North Texas Blackland Prairie, and most of the city’s housing was built as mid-century ranches and 1960s-70s tract subdivisions north and east of Dallas. Those homes have a lot going for them: solid bones, real yards, small footprints that make open-concept work worth doing. What they also have, almost without exception, is original plumbing hiding in the walls.

Installers leveling a new base cabinet during a kitchen remodel

What Does the Week-by-Week Timeline Actually Look Like?

Here’s how a Garland ranch kitchen remodel typically unfolds, with what we see on the calendar and what usually gets added. This isn’t a template. It’s the sequence we walk every homeowner through before demo day.

Phase When What Happens
Demo & rough-in inspections Week 1 Cabinets and old finishes come out, framing and utility runs are exposed, electrical and plumbing rough-ins get inspected
Electrical, plumbing, drywall Weeks 2-3 New circuits, any pipe replacement, cement board substrate (the moisture-resistant layer behind tile), drywall hang and finish
Cabinet installation Weeks 3-4 KraftMaid or Wellborn boxes go in, leveled and shimmed for an uneven floor
Countertop template & install Weeks 4-5 Template appointment after cabinets are set, then 7-10 days of fabrication (Cambria and Caesarstone both work this way)
Tile, fixtures, punch list Weeks 5-6 Backsplash, Kohler and Moen fixtures, appliance hookups, trim, final walkthrough

The fabrication queue is the phase most homeowners underestimate. Even when the whole crew is moving fast, stone countertops don’t install the day they’re measured. A stub of a wall gets in the way, a sink cutout needs a second look, and the shop has other jobs in front of yours. We build that 7-10-day window into the schedule from day one so it isn’t a surprise at week five.

What Are the Hidden-Discovery Days Nobody Warns You About?

This is the real answer behind “how long does a kitchen remodel take.” Every timeline guide lists the phases. Almost none of them account for the morning the demo crew opens a wall and finds something that has to be dealt with before drywall can ever close again.

In Garland, two discoveries come up over and over:

  • Cracked cast-iron drain lines. Older neighborhoods near downtown Garland routinely turn up original cast-iron drains with tree-root intrusion and cracks that no longer hold water. Once the wall is open, city code requires replacement.
  • Galvanized supply pipe. Mineral buildup inside galvanized lines collapses flow over decades. A fixture that “worked fine” for the last owner can go to a trickle once a new sink goes in. When the wall is open anyway, code requires replacement.

Each of those discoveries adds days. A plumber re-routes, rough-in gets inspected again, and drywall waits. If your mental calendar had zero slack in it, you’ve just lost a week you didn’t plan for.

What we do about it: our written price and written schedule account for a contingency window on pre-1975 homes before a single cabinet is pulled. We don’t guess after the fact. If we open the wall and find a problem, the number on the invoice matches the number in the schedule, or we’re on the phone with you that same afternoon. That’s what The Kingswell Way means in practice: say the price before the work, show up in the window we gave, leave the place cleaner than we found it.

A remodeled primary suite with built-in wardrobes and a window seat

Why Do the Materials Dictate the Calendar More Than the Crew?

The single biggest timeline killer in a Garland kitchen remodel is starting demo before the cabinets are ordered. We see it constantly when we’re brought in to pick up a stalled job, and it’s always the same story: the boxes never arrived, and the homeowner has been eating off a card table in the living room for a month.

The reality:

  • Cabinets: KraftMaid and Wellborn both run 3-5 weeks from order to delivery. That clock starts the day you sign, not the day the crew shows up.
  • Countertops: Cambria and Caesarstone can’t be fabricated until after cabinets are set and a template appointment happens. From there, add 7-10 days for the shop. A stone counter is measured after installation, not before.
  • Fixtures and finishes: A Kohler or Moen fixture on backorder can stall the final walkthrough, so anything with a lead time gets ordered the week the contract is signed.

The schedule we hand you includes material order dates and the permit milestones already mapped out, so the countertop fabricator’s slot gets booked before demo, not during it.

Can a Permit Delay Really Add a Week?

Yes, and it’s entirely preventable. Garland’s Development Services requires electrical and plumbing rough-in inspections before the walls close up. If the permit wasn’t pulled before demo began, you’re stuck waiting for an inspection opening, and that can add 3-7 days to the front end of the job. A contractor who pulls the permit first and schedules the inspection on the day the rough-in is ready keeps the calendar intact. One who waits until the wall is open doesn’t. It’s that simple, and it’s why we build permit milestones into the written schedule from day one.

How Much Does a Kitchen Remodel Cost in Garland?

A full kitchen remodel in Garland runs $14,000-$45,000 depending on layout, cabinet line, and countertop material. A small kitchen remodel lands in the $9,000-$20,000 range. For a single piece of the job:

  • Cabinet installation: $4,000-$13,000
  • Countertop installation: $2,000-$6,500
  • Backsplash installation: $800-$2,500
  • Kitchen island installation: $3,000-$10,000

Those ranges are real numbers, not a teaser. When we walk your Garland kitchen, we hand you a written price before work starts: the same number you’ll see on the invoice. If we find a cracked cast-iron drain or a failing sill plate after demo, we call you before touching anything else so you can see the reality and approve the fix. No surprise line items after the wall is open.

Each Penhallow location is independently owned and operated as part of the Kingswell family of companies, and every project comes with the 365-Day Done Right Promise in writing. If something we installed fails within the year, we come back and fix it at no charge. No re-inspection fee, no service call fee. And the products we install carry their own manufacturer warranties alongside ours, so the layers of protection stack up.

FAQs

Where to Go From Here

If you’d rather have it looked at, Penhallow Remodeling Garland offers a no-pressure assessment in Garland. We’ll walk your kitchen, tell you what to expect from the timeline, and put the price and schedule in writing before any work begins. Call (844) 560-4146 to get started. Our technicians have up to 22 years of experience, arrive background-checked and in uniform, and we back every job with a 365-day written guarantee. You can also read more about our broader Kitchen Remodeling work or see the full Kitchen Remodeling in Garland service page.

Written by the team at Penhallow Remodeling Garland, serving Garland, TX.

Getting started with Penhallow in Garland

Every project starts with a conversation and a written price. Here is how to take the first step.

A project lead measuring a kitchen with the homeowner during a free estimate

Free on-site estimate

A project lead walks the job with you, measures it and hands you a written, line-item price. No obligation.

Book an estimate
A remodeling crew arriving at a home with lumber and tools

Your Garland team

A local vetted partner works across Garland and the towns around it, to the same written standard as every Penhallow job.

Areas we serve
A worker laying floor protection and a dust barrier before work starts

Read our written promise

What we promise on every job, written down, with the terms spelled out before any work starts.

Our promise
Need Construction help in Garland? Licensed & insured · free written estimates
Call (844) 560-4146
Local Service Coverage

Request a Free Estimate in Garland

Tell us what you need - Penhallow Remodeling Garland responds fast. No obligation.

By submitting this form you agree to our Privacy Policy and consent to be contacted by phone, email or SMS about your request, including by local professionals who may handle it.

Prefer to text? Text Now
Call Now - 24/7 Dispatch